Third presentations are coming up, so many objectives are needed to be done. Below is the list of tasks that are being taken care of leading up to the third presentation.

1) Solidworks drawings are being finalized for the mounting system for the solar panels.

2) Calculations are evaluated for accuracy, and put into a spreadsheet to display.

3) Researching materials and costs (bill of materials).

5) Distribute our information to other groups as well acquire information from them so that everyone is on the same page, and can make modifications if need to.

4) Begin preparation for the report.

Other than that, intermediate solar group is well organized and working on schedule to complete the tasks that are needed to provide the intermediate scale power that they need.